24 Hour Hotline (808) 292-8377

Project Schedule

November 2016 – November 2017
New Bridge Construction

July 2016 – December 2016
New Freeway Ramp Excavation and Utilities

August 2016 – October 2016
Utility Relocations along H1

September 2016 – December 2016
Overpass Drilled Shafts

October 2016 – December 2016
H1 Shoulder Modifications

November 2016 – May 2017
Overpass Columns

July 2016 – November 2017
New Freeway Ramp Construction

April 2017- December 2017
Overpass Bridge Deck

November 2017 – May 2018
Existing Farrington HWY Overpass Modifications

November 2017 – May 2018
New H1 Freeway Signs and Guardrail

September 2016 – June 2017
Farrington HWY Widening

Project End : May 2018