24 Hour Hotline (808) 342-5575

Traffic Control

H-1 Eastbound Left Lane between Laaloa Street and Campbell Industrial Park On-ramp

Work dates: From 7/14/19 (Sunday night) to 7/19/19 (Friday morning)
Hours of closure: 8:30 PM TO 4:30 AM

H-1 Westbound 2 Right Lanes between Kualaka'i Parkway Off-ramp and Makakilo Drive Off-ramp

Work dates: From 7/18/19 (Thursday night) to 7/19/19 (Friday morning)
Hours of closure: 9:00 PM TO 5:00 AM

H-1 Eastbound Exit 1A Closure - Campbell Industrial Park Off-ramp

Work dates: From 7/16/19 (Tuesday night) to 7/19/19 (Friday morning)
Hours of closure: 10:00 PM TO 4:00 AM
See attached detour map

H-1 Westbound Full Closure between Makakilo Drive Off-ramp to Campbell Industrial Park Off-ramp

Work dates: From 7/15/19 (Monday night) to 7/16/19 (Tuesday morning)
Hours of closure: 10:00 PM TO 5:00 AM
See attached detour map

H-1 Westbound Left Lane between Makakilo Drive On-ramp and Farrington Highway Off-ramp

Work dates: 7/16/19 (Tuesday) to 7/19/19 (Friday)
Hours of closure: 8:30 AM TO 3:00 PM

H-1 Eastbound Left Lane between Farrington Highway Overpass and Makakilo Drive On-ramp

Work dates: 7/16/19 (Tuesday) to 7/19/19 (Friday)
Hours of closure: 8:30 AM TO 3:00 PM

Project Schedule

November 2017 – November 2019
Existing Farrington HWY Overpass Modifications

September 2018 – November 2019
New Freeway Ramp Construction

January 2019 – November 2019
Overpass Bridge Deck

July 2018 – November 2019
New H1 Freeway Sign Foundations and Guardrail

Project End: November 2019

See Full Schedule